DCA invites you to submit a proposal for Research Consultant – “Socio-Economic Impact of Humanitarian Mine Action in Sirte - LIBYA”
Dear Sir/Madam,
The Service is required for Research Consultant – “Socio-Economic Impact of Humanitarian Mine Action in Sirte - Libya” an intervention supported by FCO. Please find enclosed the following documents which constitute the Request for Proposal:
A – Instructions
Annex 1: Terms of Reference
Annex 2:Proposal Financial submission form
Annex 3: General Terms and Conditions for Service Contracts – Ver2 2012
Annex 4: Code of Conduct for Contractors
If this document is a PDF format, upon request, a complete copy of the above documents can be forwarded in a WORD format for electronic completion. It is forbidden to make alterations to the text.
We should be grateful if you would inform us by email of your intention to submit or not a proposal.
A. Instructions
In submitting a proposal, the Candidate accepts in full and without restriction the special and general conditions including annexes governing this Contract as the sole basis of this procedure, whatever his own conditions of services may be, which the Candidate hereby waives. The Candidates are expected to examine carefully and comply with all instructions, forms, contract provisions and specifications contained in this Request for Proposal.
A.1.Scope of services
The Services required by the Contracting Authority are described in the Terms of Reference in Annex 1.
The Candidate shall offer the totality of the Services described in the Terms of Reference. Candidates offering only part of the required Services will be rejected.
A.2.Cost of proposal
The Candidate shall bear all costs associated with the preparation and submission of his proposal and the Contracting Authority is not responsible or liable for these costs, regardless of the conduct or outcome of the process.
A.3.Eligibility and qualification requirements
Candidates are not eligible to participate in this procedure if they are in one of the situations listed in article 33 of the General Terms and Conditions for Service Contracts – Ver2 2012.
Candidates shall in the Proposal Submission Form attest that they meet the above eligibility criteria. If required by the Contracting Authority, the Candidate whose proposal is accepted shall further provide evidence satisfactory to the Contracting Authority of its eligibility.
As a rule, the arrival of a proposal in due time is always the candidates responsibility. Late proposals refer to any proposal arriving after the Closing date for submitting proposals, and any proposals arriving late due to a delay, for instance, in the delivery of mail or due to a technical problem related to electronic data transmission.
Candidates are also requested to certify that they comply with the Code of Conduct for Contractors.
A.4.Exclusion from award of contracts
Contracts may not be awarded to Candidates who, during this procedure:
(a) are subject to conflict of interest
(b) are guilty of misrepresentation in supplying the information required by the Contracting Authority as a condition of participation in the Contract procedure or fail to supply this information
A.5.Documents comprising the Request for Proposal
The Candidate shall complete and submit the following documents with his proposal:
- Technical Proposal based on the candidate preferred format
- Proposal Submission Form based on Annex 2.
- CV. highlighting the Candidate’s experience in the specific field of the Services and his/her specific experience in the country/region where the Services are to be performed;
The proposal and all correspondence and documents related to the Request for Proposal exchanged by the Candidate and the Contracting Authority must be written in the language of the procedure, which is English.
A.6.Financial proposal
The Financial Proposal shall be presented as an amount in EUR. The remuneration of the Candidate under the Contract shall be determined as follows:
The Candidate shall indicate in his/her proposal his/her proposed global remuneration for the performance of the Services. The Candidate shall be deemed to have satisfied himself as to the sufficiency of his/her proposed global remuneration, to cover both his/her fee rate, including overhead, profit, all his/her obligations, sick leave, overtime and holiday pay, taxes, social charges, etc. and all expenses (such as transport, accommodation, food, office, etc.) to be incurred for the performance of the Contract. The proposed global remuneration shall cover all obligations of the successful Candidate under the Contract (without depending on actual time spent on the assignment) and all matters and things necessary for the proper execution and completion of the Services and the remedying of any deficiencies therein.
VAT and/or any sales tax applicable to the purchase of services shall be indicated separately in the proposal.
A.7.Validity
Proposals shall remain valid and open for acceptance for 30 days after the closing date.
A.8.Submission of proposals and closing date
Proposals must be received at the address mentioned on the front page by email not later than the closing date and time specified on the front page.
A.9.Evaluation of Proposals
The evaluation method will be the quality and cost-based selection. A two-stage procedure shall be utilised in evaluating the Proposals; a technical evaluation and a financial evaluation.
Proposals will be ranked according to their combined technical (St) and financial (Sf) scores using the weights of 75% for the Technical Proposal; and 25% for the offered price. Each proposal’s overall score shall therefore be: St X 75% + Sf X 25%.
Technical evaluation
For the evaluation of the technical proposals, the Contracting Authority shall take the following criteria into consideration, with the indicated weights:
Technical evaluation
Maximum Points
Candidate
A
B
C
D
E
Expertise of the Candidate submitting proposal
1
(Candidate’s specialised knowledge and experience in the field of assignment and selected region
10
2
(Candidate’s relevant experience in the field of assignment)
10
3
(Candidate’s experience in the region/country e.g. knowledge of local language, culture, administrative system, government etc.)
5
4
(Candidate’s proficiency in Arabic language)
5
5
(To what degree does the proposal show understanding of the task?)
15
6
(Have the Terms of Reference been addressed in sufficient detail?)
15
7
(Is the conceptual framework adopted appropriate for the task?)
10
8
(Is the sequence of activities and the planning logical, realistic and promising efficient implementation to the Contract?)
15
9
(Is the work plan adequate in responding to the Terms of Reference)
15
Total Technical Score
100
Interviews
The Contracting Authority reserves the right to call to interview the Candidates having submitted proposals determined to be substantially responsive.
Financial evaluation
Each proposal shall be given a financial score. The lowest Financial Proposal (Fm) will be given a financial score (Sf) of 100 points. The formula for determining the financial scores shall be the following:
Sf = 100 x Fm/F, in which
Sf is the financial score
Fm is the lowest price and
F is the price of the proposal under evaluation
Negotiations
The Contracting Authority reserves the right to contact the Candidates having submitted proposals determined to be substantially and technically responsive, in order to propose a negotiation of the terms of such proposals. Negotiations will not entail any substantial deviation to the terms and conditions of the Request for Proposal, but shall have the purpose of obtaining from the Candidates better conditions in terms of technical quality, implementation periods, payment conditions, etc.
Negotiations may however have the purpose of reducing the scope of the services or revising other terms of the Contract in order to reduce the proposed remuneration when the proposed remunerations exceed the available budget.
A.12. Award criteria**
The Contracting Authority will award the Contract to the Candidate whose proposal has been determined to be substantially responsive to the documents of the Request for Proposal and which has obtained the highest overall score.
A.13.Signature and entry into force of the Contract
Prior to the expiration of the period of the validity of the proposal, the Contracting Authority will inform the successful Candidate in writing that its proposal has been accepted and inform the unsuccessful Candidates in writing about the result of the evaluation process.
Within 5 days of receipt of the Contract, not yet signed by the Contracting Authority, the successful Candidate must sign and date the Contract and return it to the Contracting Authority. On signing the Contract, the successful Candidate will become the Contractor and the Contract will enter into force once signed by the Contracting Authority.
If the successful Candidate fails to sign and return the Contract within the days stipulated, the Contracting Authority may consider the acceptance of the proposal to be cancelled without prejudice to the Contracting Authority's right to claim compensation or pursue any other remedy in respect of such failure, and the successful Candidate will have no claim whatsoever on the Contracting Authority.
A.14.Cancellation for convenience
The Contracting Authority may for its own convenience and without charge or liability cancel the procedure at any stage.
Annex 1: Terms of reference
Background
DCA Libya has successfully implemented Humanitarian Mine Action (HMA) programming, including ERW Clearance and Mine Risk Education, in the city of Sirte since 2017. To support its programming as well as study the impact of their two-year programme, DCA Libya invites interested candidates to apply for the role as research consultant to conduct a 5-month study on the socio-economic impact of the HMA activities in Sirte. The ideal candidate can design and execute a detailed analysis of the impact and report these in a way that can be further disseminated to stakeholders.
OBJECTIVE OF MATERIAL
The findings of the study are targeted to donors, decision makers and relevant stakeholders working on Libya programming, as well as DCA staff members to utilize the study for further project development. The objectives are:
· To conduct a socio-economic impact study on the effects of humanitarian mine action programme in Sirte
· To present the study to international donor and INGO community during a presentation to share, advocate and inform stakeholders
· To utilize the report for lessons learned and priority setting for continuation of operations in Sirte and other areas in Libya
DESCRIPTION OF WORK
DCA Libya proposes to conduct a socio-economic study with the focus on an in-depth measurement of the impact of humanitarian mine action in the city of Sirte. This will be used to measure the impact on the socio-economic situation of communities, including their access to basic services, increase in livelihoods, and the work’s contribution to the goals outlined in the agenda for sustainable development (SDGs).
The findings of the report will enable DCA to assist the municipality of Sirte in setting priorities in developing plans to further recover the city and its infrastructure. More so, it will also help to monitor and analyse in what way DCA’s programming impacts livelihoods, access and safety and security in Sirte. Lastly, by presenting the findings to a wider community of stakeholders in Sirte, INGO and the donor community, will help advocate for further support of development programming in Central-Libya.
During phase one of the project, the research consultant will complete an inception report and desk study, including the development of the methodology and work plan of the study. For the first period, the consultant will be based in Tunis. The workplan should also include (remote) preparation of logistics, including the scheduling of focus group discussions, development of surveys, liaising with the Sirte Municipal Council, as well as enable further collection of data to complete the desk study and inception report.
Phase two will see the recruitment of 10 students from Sirte University who will be trained in mobile data collection. Under the (remote) supervision and guidance of the research consultant, this team will complete survey collection, facilitate focus group discussions and hold beneficiary interviews. In addition, they will support the consultant in data reviewing, data processing and the drafting of the report. While the data is being collected, the research consultant will oversee all incoming data and commence writing the final report to be finalized by March/April 2020.
Phase three will see the design and publication of the final report. It is possible that a designer will be hired to design a visually attractive report that can be published digitally, as well as be printed in hard-copy, however the consultant should be able to deliver a presentable report in Microsoft Word format. After approval, this report will then be presented at a presentation organized by DCA, bringing stakeholders and interested parties together to share findings on the impact of HMA and connect this to the sustainable development goals.
With the current volatile situation in Libya ongoing, the consultant should be prepared to complete the entire study remotely (through support of Libya based DCA staff members).
EXPECTED OUTPUTS
Output 1: An Inception Report including a methodology and workplan to be developed within two weeks after signing of the contract.
- The methodology and workplan should provide proposed activities, timeframe, as well as key informants and institutions or organizations to be consulted to complete the tasks and achieve outputs based on the activities listed within the Description of Work above.
Output 2: The facilitation of data collection phase including:
Recruitment and training of data collection volunteers
Data collection through survey collection, key informant interviews as well as focus group discussions
Data entry into DCA Libya’s databases
Analysis of data collected during the contract duration
Output 3: A Final Report based on desk study and data collection. This includes a presentation of detailed findings and recommendations and will include:
Preparation of communication materials targeted to specific audiences to present the results of the socio-economic study
Attend a final presentation of the findings to interested international donors, mine action actors as well as other local stakeholders
Produce an accompanying briefing note that summarizes the report and recommendations that can be disseminated for awareness raising
Note: All files will remain in the property of DanChurchAid. DCA will have the copyright to the material produced by the consultant and DCA will have the right to use it on any relevant platform in the future without paying any extra fees.
COMPETENCIES, REQUIRED SKILLS AND EXPERIENCE
Competencies
• Ability to analyse complex issues, draw relevant conclusions and produce comprehensive technical reports
• An exceptionally strong ‘solutions finding’ attitude with the ability to maintain flexibility in an environment where change or revision to projects and planning is regular
• Excellent communication and consultation skills to liaise with a range of stakeholders including district and provincial authorities, local communities, private sector actors, etc. and ability and experience to conduct training.
• Ability to lead and work with teams and to achieve quality outputs under tight timelines, including those achieved through remote management
• A security conscious attitude and adherence to strict security protocols as well as diplomatic skills and cultural sensitivity
Required Skills and Experience
• Minimum of 3 years working experience or a developed knowledge of working in Middle East or North Africa required
• Demonstratable experience conducting impact studies on socio-economic related topics
• Experience of Humanitarian Mine Action programmes highly desirable
• Excellent report writing skills (in English); command of Arabic is desirable
REPORTING LINES
The research consultant will report and refer to the DCA country director, Graeme Ogilvy. On a daily basis, the research consultant will work closely with and in coordination with DCA’s programme officer and other DCA colleagues as necessary.
TIMEFRAME
The total working days to complete the study will be approximately 5 months i.e. from November 2019 until March/April 2020. Deadlines of output delivery can be decided upon between DCA Libya and the consultant. The following timeline is tentative:
Action
Timeline
Finalize and signing contract
November 2019
Travel and research days in Tunis, including desk study and inception report
November - December 2019
Output 1: An Inception Report including a methodology and workplan to be developed within two weeks after signing of the contract
1 December 2019
Output 2: Facilitation of data collection phase, including survey collection, key informant interviews and focus group discussions
January 2020 – February 2020
Analysis and report drafting phase
February – March 2020
Delivery first drafts of agreed upon product
March 2020
Output 3: Final deadline delivery end-product
April 2020
DCA Libya anticipates the selected candidate to sign a contract during November 2019 and begin work thereafter. The period of implementation of the services ranges from contract commencement date until final submission of the requested materials. The final submission of the contents of both modules need to be submitted to DCA Libya in April 2020 at a further to be discussed final date.
The consultant will initially be based in Tunis (and if preferred home-based for majority of the consultancy). The consultant will be requested to conduct the study remotely from Tunisia and as homebased, through the support of Libya based national staff and volunteers and with overall support from the administrative base in Tunis.
Annex 2: proposal submission form
My financial proposal for my services is as follows:
Currency
Amount
Global price (fees and expenses)
VAT or other tax on services
Total price incl. taxes
Candidate or Company information
Company (legal name)
Street name and no.
City
Postal code
Country
Phone no.
Website
Director (name)
REFERENCES
Name and country of customer
Type of contract
Value
Contact name
Phone/fax and email
Include details of the experience and past performance on contracts of a similar nature within the past five years and information on other contracts in hand and/or future commitments including details of the actual and effective participation in each of such contracts, description of the Candidate’s assignments and periods of engagement. Additional documents can be attached to the above form.
The proposal is valid for a period of 30 days after the closing date in accordance with the article A.7.Validity.
After having read your Request for Proposal no. 177-38/M&E for Research Consultant – “Socio-Economic Impact of Humanitarian Mine Action in Sirte - Libya” dated 28.10.2019, and after having examined the Request for Proposal, I/we hereby offer to execute and complete the services in conformity with all conditions in the Request for Proposal for the sum indicated in our financial proposal.
Further, I/we hereby:
Accept, without restrictions, all the provisions in the Request for Proposal including the General Terms and Conditions for Service Contracts - Ver2 2012 and the draft Service Contract including all annexes.
Provided that a contract is issued by the Contracting Authority I/we hereby commit to perform all services described in the Terms of Reference, Annex 1
Certify and attest compliance with eligibility criteria of article 33 of the General Terms and Conditions for Service - Ver2 2012.
Certify and attest compliance with the Code of Conduct for Contractors in Annex 4.
The above declarations will become an integrated part of the Contract and misrepresentation will be regarded as grounds for termination.
Signature and stamp:
Signed by:
The Candidate
Name of the company
Address
Telephone no.
Name of contact person
1. DEFINITIONS
In these general terms and conditions:
a) “contract” is the agreement entered into by the Contracting Authority and the Contractor for the performance of the services described in the terms of reference, to which these general terms and conditions are made applicable; the contract is constituted of the documents listed in the Service Contract.
b) The Contracting Authority’s “partners” are the organisations to which the Contracting Authority is associated or linked;
c) “personnel” is any person assigned by the Contractor to the performance of the services or any part hereof, whether through employment, sub-contracting or any other agreement; and “key experts” are those members of the personnel whose involvement is considered instrumental in the achievement of the contract objectives;
d) “beneficiary country” is the country where the services are to be performed, or where the project to which the services relate is located.
2. RELATIONS BETWEEN THE PARTIES
Nothing contained in the contract shall be construed as establishing a relation of master and servant or of agent and principal as between the Contracting Authority and the Contractor. Except if otherwise provided in the contract, the Contractor shall under no circumstances act as the representative of the Contracting Authority or give the impression that the Contractor has been given such authority. The Contractor has complete charge of the personnel and shall be fully responsible for the services performed by them.
3. SCOPE OF SERVICES
The scope of the services including the methods and means to be used by the Contractor, the results to be achieved by him and the verifiable indicators are specified in the Terms of Reference. The Contractor shall be responsible for everything which is required for the performance of the services in accordance with what is specified in the contract, or which must otherwise be regarded as forming part of the services.
4. COMPLIANCE WITH LAWS AND RESPECT OF TRADITIONS
The Contractor shall respect and abide by all laws and regulations in force in the beneficiary country and shall ensure that its personnel, their dependants, and its local employees also respect and abide by all such laws and regulations. The Contractor shall indemnify the Contracting Authority against any claims and proceedings arising from any infringement by the Contractor, its personnel and their dependants of such laws and regulations.
The Contractor, its personnel and their dependents shall respect human rights and undertake not to offend the political, cultural and religious practices prevailing in the beneficiary country.
5. CODE OF CONDUCT
The Contractor shall at all times act loyally and impartially and as a faithful adviser to the Contracting Authority and shall perform the services with due care, efficiency and diligence, in accordance with the best professional practice.
6. DISCRETION AND CONFIDENTIALITY
The Contractor shall treat all documents and information received in connection with the contract as private and confidential, and shall not, save in so far as may be necessary for the purposes of the performance thereof, publish or disclose any particulars of the contract without the prior consent in writing of the Contracting Authority. It shall, in particular, refrain from making any public statements concerning the project or the services without the prior approval of the Contracting Authority,
7. CONFLICT OF INTEREST
The Contractor shall refrain from engaging in any activity which conflicts with his obligations towards the Contracting Authority under the contract.
The Contractor shall take all necessary measures to prevent or end any situation that could compromise the impartial and objective performance of the Contract. Such conflict of interests could arise in particular as a result of economic interest, political or national affinity, family or emotional ties, or any other relevant connection or shared interest. Any conflict of interests which could arise during performance of the Contract must be notified in writing to the Contracting Authority without delay. The Contractor shall replace, immediately and without compensation from the Contracting Authority, any member of its personnel exposed to such a situation.
8. CORRUPT PRACTICES
The Contractor and the personnel shall refrain from performing, condoning or tolerating any corrupt, fraudulent, collusive or coercive practices, whether such practices are in relation with the performance of the contract or not. “Corrupt practice” means the offering, giving, receiving, or soliciting, directly or indirectly, of anything of value as an inducement or reward for doing or forbearing to do any act in relation to the contract or any other contract with the Contracting Authority, or for showing favour or disfavour to any person in relation to the contract or any other contract with the Contracting Authority.
The payments to the Contractor under the contract shall constitute the only income or benefit it may derive in connection with the contract and neither it nor its personnel shall accept any commission, discount, allowance, indirect payment or other consideration in connection with, or in relation to, or in discharge of, its obligations under the contract.
The execution of the contract shall not give rise to unusual commercial expenses. Unusual commercial expenses are commissions not mentioned in the contract or not stemming from a properly concluded contract referring to the contract, commissions not paid in return for any actual and legitimate service, commissions remitted to a tax haven, commissions paid to a recipient who is not clearly identified or commission paid to a company which has every appearance of being a front company.
The Contractor further warrants that no official of the Contracting Authority and/or their partner has received or will be offered by the Contractor any direct or indirect benefit arising from this Contract.
9. JOINT VENTURE OR CONSORTIUM
If the Contractor is a joint venture or a consortium of two or more legal persons, all such persons shall be jointly and severally bound to fulfil the terms of the contract. The person designated by the joint venture or consortium to act on its behalf for the purposes of this contract shall have the authority to bind the joint venture or consortium.
For the purposes of performance of the contract, the joint venture or consortium shall act as, and be considered, a single person and, in particular, shall have bank account opened in its name, shall submit to the Contracting Authority single guarantees if required, and shall submit single invoices and single reports.
The composition of the joint venture or a consortium shall not be altered without the prior written consent of the Contracting Authority.
10. SPECIFICATIONS AND DESIGNS
The Contractor shall prepare all specifications and designs using accepted and generally recognised systems acceptable to the Contracting Authority and taking into account the latest design criteria.
11. INFORMATION
The Contractor shall furnish the Contracting Authority or any person authorised by the Contracting Authority with any information relating to the services and the project as the Contracting Authority may at any time request.
12. REPORTS
The frequency, deadlines, format and contents of the reports to be drawn up by the Contractor in relation to the performance of the contract shall be described in the Terms of Reference.
13. CONTRACTOR’S PERSONNEL
13.1. The Contractor shall employ and provide such qualified and experienced personnel as are required to carry out the services, and the Contractor shall be responsible for the quality of the personnel.
The names, outputs, duties and CVs of key experts and the titles, job descriptions, minimum qualifications, estimated periods of engagement in the carrying out of the services of each of the personnel and key experts are described in the Organisation and Methodology part of the contract. The Contractor must inform the Contracting Authority of all non-expert personnel it intends to use for the implementation of the contract. The Contracting Authority shall have the right to oppose the Contractor’s choice of personnel.
13.2. No changes shall be made in the personnel without the prior consent of the Contracting Authority. The Contractor shall provide a replacement with at least equivalent qualifications and experience and acceptable to the Contracting Authority if:
a) on account of death, sickness or accident, a member of the Personnel is unable to continue providing his services,
b) any member of the personnel is found by the Contracting Authority to be incompetent in discharging or unsuitable for the performance of his duties under the Contract,
c) for any reasons beyond the control of the Contractor, it becomes necessary to replace any member of the Personnel.
The request for replacement must be made in writing and state the reasons therefore. The Contractor shall proceed swiftly with the request and propose a replacement with at least equivalent qualifications and experience. The remuneration to be paid to the replacement cannot exceed that received by the replaced member of the personnel.
Failure by the Contractor to propose a replacement for a key expert satisfactory to the Contracting Authority, shall give the right to the Contracting Authority to terminate the contract.
Additional costs arising out of a replacement shall be borne by the Contractor.
13.3. Working hours
The days and hours of work of the Contractor or/and its personnel in the beneficiary country shall be fixed on the basis of the laws, regulations and customs of the beneficiary country and the requirements of the services.
13.4. Leave entitlement
Any taking of holiday leave by the personnel during the period of implementation of the contract must be at a time approved by the Contracting Authority.
Overtime, sick leave pay and holidays leave pay are deemed to be covered by the Contractor’s remuneration.
14. SUB-CONTRACTING
Except from the subcontractors listed in the contract, the Consultant shall not subcontract to nor engage another independent contractor to perform any part of the services without the prior written consent of the Contracting Authority. Subcontractors must satisfy the eligibility criteria applicable for the award of the contract.
The Contracting Authority shall have no contractual relations with the subcontractors. The provisions of the contract, including these general terms and conditions, and in particular article 13.2 shall, where practicable, apply to the subcontractors and their personnel.
15. LIABILITY
At its own expense, the Contractor shall indemnify, protect and defend, the Contracting Authority, its agents and employees, from and against all actions, claims, losses or damages arising from any act or omission by the Contractor in the performance of the services, including any violation of any legal provisions, or rights of third parties, in respect of patents, trademarks and other forms of intellectual property such as copyrights.
Approval by the Contracting Authority of the Contractor’s reports and issue of Completion Certificate shall not relieve the Contractor of its liability and shall not prevent the Contracting Authority from claiming damages.
The Contractor shall remain liable for any breach of its obligations under the contract for such period after the services have been performed as may be determined by the law governing the contract (the “liability period”). This time limit does not however apply when the damage arises from gross negligence or wilful misconduct of the Contractor.
During the liability period, or as soon as practicable after its expiration, the Contractor shall, at its expense, upon instruction of the Contracting Authority, remedy any deficiencies in the performance of the services. In case of default on the part of the Contractor to carry out such instructions, the Contracting Authority shall be entitled to hire another contractor to carry out the same, at the Contractor’s expense.
16. INSURANCE
Within 20 days of signing the contract, the Contractor shall take out and maintain, at its own cost, a full indemnity insurance policy covering its professional liability under the contract and article 15 above, from the commencement date and until the end of the liability period.
Within 20 days of signing the contract, the Contractor shall take out and maintain a full indemnity insurance policy for a sum up to the higher of the maximum amount foreseen by the legislation of the country of the Contracting Authority and the amount foreseen by the legislation of the country in which the Contractor has its headquarters and covering, during the period of implementation of the contract, the following risks:
a) loss of or damage to property purchased with funds provided under the contract, or produced by the Contractor;
b) loss or damage to equipment, material and office facilities made available to the Contractor by the Contracting Authority;
c) civil liability for accidents caused to third parties arising out of acts performed by the Contractor, its personnel and their dependents;
d) employer’s liability and workers’ compensation in respect of the personnel as well as sickness, accident or death affecting the personnel and their dependents, including the cost of repatriation on health grounds;
e) such other insurance as required by the laws in force in the beneficiary country.
Prior to the commencement date, the Contractor shall provide evidence to the Contracting Authority that the above insurances have been effected. During execution of the contract, the Contractor shall, when required, provide the Contracting Authority with copies of the insurance policies and the receipts for payment of premiums.
17. INTELLECTUAL AND INDUSTRIAL PROPERTY RIGHTS
All reports and data such as maps, diagrams, drawings, specifications, plans, statistics, calculations, databases, software and supporting records or materials acquired, compiled or prepared by the Contractor in the performance of the contract shall, with the copyright thereto, be the absolute property of the Contracting Authority. The Contractor shall, upon completion of the contract, deliver all such documents and data to the Contracting Authority. The Contractor may not retain copies of such documents and data and shall not use them for purposes unrelated to the contract without the prior written consent of the Contracting Authority.
The Contractor shall not publish articles relating to the services or refer to them when carrying out any services for others, or divulge information obtained from the Contracting Authority, without the prior written consent of the Contracting Authority.
18. RECORDS
The Contractor shall keep separate, accurate and systematic records and accounts in respect of the services in such form and detail as is customary in the profession and sufficient to establish accurately that the number of working days and the actual reimbursable expenditure identified in the Contractor's invoice(s) have been duly incurred for the performance of the services.
For a fee-based contract, timesheets recording the days worked by the Contractor's personnel must be maintained by the Contractor. The timesheets must be approved by the Contracting Authority or any person authorised by the Contracting Authority or the Contracting Authority itself on a monthly basis. The amounts invoiced by the Contractor must correspond to these timesheets. In the case of long-term experts, these timesheets must record the number of days worked. In the case of short-term experts, these timesheets must record the number of hours worked. Time spent travelling exclusively and necessarily for the purpose of the Contract may be included in the numbers of days or hours, as appropriate, recorded in these timesheets.
Such records must be kept for a 7-year period after the final payment made under the contract. These documents comprise any documentation concerning income and expenditure and any inventory, necessary for the checking of supporting documents, including timesheets, plane and transport tickets, pay slips for the remuneration paid to the experts and invoices or receipts for reimbursable expenditure. Failure to maintain such records constitutes a breach of contract and will result in the termination of the contract.
19. OBLIGATIONS OF CONTRACTING AUTHORITY
19.1. The Contracting Authority shall provide the Contractor as soon as possible with any information and/or documentation at its disposal which may be relevant to the performance of the contract.
On all matters properly referred to it in writing by the Contractor, the Contracting Authority shall give its decisions so as not to delay the services, and within a reasonable time.
19.2. The contract shall specify whether the Contracting Authority is to provide the Contractor with equipment, facilities, counterpart personnel or specific assistance, and shall detail under which conditions. If the provision of such agreed counterpart personnel, equipment, facilities and assistance is delayed or not forthcoming, the Contractor shall endeavour to perform the Services as far as is possible. The parties shall agree on how the affected parts of the services shall be carried out, and the additional payments, if any is due, to be made by the Contracting Authority to the Contractor as a result of additional expenditures.
20. CONTRACT PRICE AND PAYMENTS
Contracts are either “global price” or “fee-based”.
20.1. Fee-based contract
In consideration of the services performed by the Contractor under the contract, the Contracting Authority shall make to the Contractor such payments of fees and such reimbursement of costs as provided in the contract.
Fees shall be determined on the basis of time actually spent by the key experts in the performance of services at the fee rates specified in the contract. Fee rates are deemed to remunerate all the activities of the Contractor in the performance of the services and to cover all expenses and costs incurred by the Contractor which are not included in the agreed reimbursable costs.
The Contracting Authority shall reimburse to the Contractor the reimbursable costs and expenses specified in the contract, actually and reasonably incurred in the performance of the services.
Costs and expenses which are not mentioned in the contract shall be deemed covered by the overhead of profit included in the fees.
The currency of payments of fees and reimbursable costs and applicable exchange rates are set out in the contract.
20.2. Global price contract
The global price covers both the Contractor’s and its personnel’s fees and all expenses to be incurred for the performance of the contract. The global price is in consideration for all obligations of the Contractor under the contract and all matters and things necessary for the proper execution and completion of the services and the remedying of any deficiencies therein.
20.3. Revision
Unless otherwise stipulated in the contract, the global price of a global price contract and the fee rates of a fee-based contract shall not be revised.
20.4. Guarantees
In the case an advance payment for fees and for reimbursable costs (fee-based contract) or a pre-financing payment (global price contract) is agreed in the contract, its payment by the Contracting Authority shall be subject to the prior presentation by the Contractor to the Contracting Authority of an approved performance security, advance payment or pre-financing guarantee, if so agreed and under the conditions specified in the Service Contract.
20.5. Conditions of Payment
Payments will be made by the Contracting Authority with the frequency, instalments, time limits, amounts and currencies, and under the conditions, in particular on the contents of invoices, specified in the special conditions of the contract. Payment of the final balance shall be subject to performance by the Contractor of all its obligations under the contract and the issue by the Contracting Authority of the completion certificate described in article 25.
20.6. Late payment
If the time periods laid down for payments by the Contracting Authority have been exceeded by more than two months and where the Contracting Authority cannot invoke a case of suspension or withholding of payments provided for in these terms and conditions, the Contractor may claim interest calculated on any amount due, prorate on the number of days of delay at the official bank rate of the beneficiary country (if amounts due are in the currency of that country), or at the rate applied by the European central bank (where amounts due are in Euro), plus 2% per year.
21. DELAYS IN PERFORMANCE
If the Contractor does not perform the services within the period of implementation specified in the contract, the Contracting Authority shall, without formal notice and without prejudice to its other remedies under the contract, be entitled to liquidated damages for every day, or part thereof, which shall elapse between the end of the period of implementation specified in the contract and the actual end of the period of implementation.
The daily rate for liquidated damages is calculated by dividing the contract value by the number of days of the period of implementation.
If these liquidated damages exceed more than 15% of the contract value, the Contracting Authority may, after giving notice to the Contractor:
a) terminate the contract; and
b) complete the services at the Contractor's own expense
22. BREACH OF CONTRACT
Either party commits a breach of contract where it fails to discharge any of its obligations under the contract.
Where a breach of contract occurs, the party injured by the breach shall be entitled to the following remedies:
a) liquidated damages; and/or
b) termination of the contract.
In any case where the Contracting Authority is entitled to damages, it may deduct such damages from any sums due to the Contractor or call on the appropriate guarantee.
The Contracting Authority shall be entitled to compensation for any damage which comes to light after the contract is completed in accordance with the law governing the contract.
23. SUSPENSION OF PERFORMANCE
The Contractor shall, on the request of the Contracting Authority, suspend the performance of the services or any part thereof for such time and in such manner as the Contracting Authority may consider necessary.
In such event of suspension, the Contractor shall take immediate action to reduce the costs incident to the suspension to a minimum. During the period of suspension, and except where the suspension is due to any default of the Contractor, the Contractor shall be reimbursed for additional costs reasonably and necessarily incurred by it as a result of the suspension.
24. AMENDMENT OF THE CONTRACT
Substantial modifications to the contract, including modifications to the total contract amount, must be made by means of an addendum.
25. Completion Certificate
Upon completion of the services, and once (a) the Contracting Authority has approved the Contractor’s completion report, (b) the Contracting Authority has approved the Contractor’s final invoice and final audited statement, the Contracting Authority shall deliver a completion certificate to the Contractor.
26. TERMINATION BY THE CONTRACTING AUTHORITY
26.1 The Contracting Authority may terminate the contract after giving a 7 days' notice to the Contractor in any of the following cases:
a) the Contractor is in breach of its obligations under the contract and/or fails to carry out the services substantially in accordance with the contract;
b) the Contractor fails to comply within a reasonable time with the notice given by the Contracting Authority requiring it to make good the neglect or failure to perform its obligations under the contract which seriously affects the proper and timely performance of the services;
c) the Contractor refuses or neglects to carry out instructions given by the Contracting Authority;
d) the Contractor’s declarations in respect if its eligibility (article 33) and/or in respect of article 31 and article 32, appear to have been untrue, or cease to be true;
e) the Contractor takes some action without requesting or obtaining the prior consent of the Contracting Authority in any case where such consent is required under the contract;
f) any of the key experts is no longer available, and the Contractor fails to propose a replacement satisfactory to the Contracting Authority;
g) any organisational modification occurs involving a change in the legal personality, nature or control of the Contractor or the joint venture or consortium, unless such modification is recorded in an addendum to the contract;
h) the Contractor fails to provide the required guarantees or insurance, or the person providing the underlying guarantee or insurance is not able to abide by its commitments.
26.2 Termination by Contracting Authority for convenience
The Contracting Authority may terminate the contract in whole or in part for its convenience, upon not less than 14 days’ notice. The Contracting Authority shall not use this right of termination in order to arrange for the services to be executed by another contractor, or to avoid a termination of the contract by the Contractor.
27. TERMINATION BY THE CONTRACTOR
The Contractor may terminate the contract after giving a 7 days’ notice to the Contracting Authority in any of the following cases:
a) the Contractor has not received payment of that part of any invoice which is not contested by the Contracting Authority, within 90 days of the due payment date,
b) the period of suspension of the performance of the contract under article 23 has exceeded six months;
c) the Contracting Authority is in material breach of its obligations under the Contract and has not taken any actions to remedy the same within 30 days following the receipt by the Contracting Authority of the Contractor’s notice specifying such breach.
If the Contractor is a natural person, the contract shall be automatically terminated if that person dies.
28. RIGHTS AND OBLIGATIONS UPON TERMINATION
28.1. Upon termination of the contract by notice of either party to the other, the Contractor shall take immediate steps to bring the services to a close in a prompt and orderly manner and in such a way as to keep costs to a minimum.
28.2. If the Contracting Authority terminates the contract in accordance with article 26.1 it may, thereafter, complete the services itself, or conclude any other contract with a third party, at the Contractor’s expense.
The Contracting Authority shall, as soon as is possible after termination, certify the value of the services and all sums due to the Contractor as at the date of termination. It shall, subject to article 28.1 and 28.3, make the following payments to the Contractor:
(a) remuneration pursuant to the contract for services satisfactorily performed prior to the effective date of termination;
(b) reimbursable costs (if fee-based contract) for costs actually incurred prior to the effective date of termination;
(c) except in the case of termination pursuant to article 26.1 reimbursement of any reasonable cost incident to the prompt and orderly termination of the contract;
(d) in case of termination under article 26.2 and 27, reimbursement for the actual and reasonable costs incurred by the Contractor as a direct result of such termination and which could not be avoided or reduced by appropriate mitigation measures.
The Contractor shall not be entitled to claim, in addition to the above sums, compensation for any loss or injury suffered.
28.3. In case of termination of the contract for any reason whatsoever, any pre-financing guarantee which might have been granted to the Contracting Authority under article 20.4, may be invoked forthwith by the Contracting Authority in order to repay any balance still owed to the Contracting Authority by the Contractor, and the guarantor shall not delay payment or raise objection for any reason whatever.
28.4. If the Contracting Authority terminates the contract under article 26.1, it shall be entitled to recover from the Contractor any loss it has suffered up to that part of the contract value which corresponds to that part of the services which has not, by reason of the Contractor’s default, been satisfactorily completed.
29.FORCE MAJEURE
Neither party shall be considered to be in breach of its obligations under the contract if the performance of such obligations is prevented by any circumstances of force majeure which arise after the date of signature of the contract by both parties.
The term "force majeure", as used herein shall mean acts of God, strikes, lock-outs or other industrial disturbances, acts of the public enemy, wars, whether declared or not, blockades, insurrection, riots, epidemics, landslides, earthquakes, storms, lightning, floods, washouts, civil disturbances, explosions, and any other similar unforeseeable events, beyond the control of either party and which by the exercise of due diligence neither party is able to overcome.
A party affected by an event of force majeure shall take all reasonable measures to remove such party's inability to fulfil its obligations hereunder with a minimum of delay.
If either party considers that any circumstances of force majeure have occurred which may affect performance of its obligations it shall notify the other party immediately giving details of the nature, the probable duration and likely effect of the circumstances. Unless otherwise directed by the Contracting Authority in writing, the Contractor shall continue to perform its obligations under the contract as far as is reasonably practicable, and shall seek all reasonable alternative means for performance of its obligations which are not prevented by the force majeure event. The Contractor shall not put into effect such alternative means unless directed so to do by the Contracting Authority.
30. APPLICABLE LAW AND DISPUTES
The contract is governed by, and shall be construed in accordance with the laws of the Contracting Authority’s country.
Any dispute or breach of contract arising under this contract shall be solved amicably if at all possible. If not possible and unless provided in the Service Contract, it shall be settled finally by court decision, which shall be held under the law of the Contracting Authority’s country. Any ruling by the court will be final and directly executable in the country of the Contractor.
31. CHILD LABOUR AND FORCED LABOUR
The Contractor (and each member of a joint venture or a consortium) warrants that it and its affiliates comply with the UN Convention on the Rights of the Child - UNGA Doc A/RES/44/25 (12 December 1989) with Annex – and that it or its affiliates has not made or will not make use of forced or compulsory labor as described in the Forced labor Convention and in the Abolition of Forced Labor Convention 105 of the International Labor Organization. Furthermore the Contractor warrants that it, and its affiliates, respect and uphold basic social rights and working conditions for its employees. Any breach of this representation and warranty, in the past or during the performance of the contract, shall entitle the Contracting Authority to terminate this contract immediately upon notice to the Contractor, at no cost or liability for the Contracting Authority.
32. MINES
The Contractor and each member of the joint venture or a consortium) warrants that it and its affiliates is NOT engaged in any development, sale or manufacture of anti-personnel mines and/or cluster bombs or components utilized in the manufacture of anti-personnel mines and/or cluster bombs. Any breach of this representation and warranty shall entitle the Contracting Authority to terminate this contract immediately upon notice to the Contractor, at no cost or liability for the Contracting Authority.
33. INELIGIBILITY
By signing the purchase order, the Contractor (or, if a joint venture or a consortium, any member thereof) certifies that they are NOT in one of the situations listed below:
(a) They are bankrupt or being wound up, are having their affairs administrated by courts, have entered into an agreement with creditors, have suspended business activities, are the subject of proceedings concerning house matters, or are in any analogous situation arising from a similar procedure provided for in national legislation or regulations;
(b) They have been convicted of an offence concerning their professional conduct by a judgement that has the force of res judicata;
(c) They have been guilty of grave professional misconduct proven by any means that the Contracting Authority can justify;
(d) They have not fulfilled obligations relating to the payment of social security contributions or payment of taxes in accordance with the legal provisions of the country in which they are established or with those of the country of the Contracting Authority or those of the country where the contract is to be performed;
(e) They have been the subject of a judgement that has the force of res judicata for fraud, corruption, involvement in a criminal organisation or any other illegal activity detrimental to the Contracting Authority or the European Community’s financial interests;
(f) Following another procurement procedure or grant award procedure financed by the European Community budget or following another procurement procedure carried out by the Contracting Authority or one of their partners, they have been declared to be in serious breach of contract for failure to comply with their contractual obligations.
34. CHECKS AND AUDITS
The Seller shall permit the Contracting Authority or its representative to inspect, at any time, records including financial and accounting documents and to make copies thereof and shall permit the Contracting Authority or any person authorized by it, including USAID, the European Commission, the European Anti-Fraud Office and the Court of Auditors in case the Contract is financed by USAID or the European Community budget, at any time, to have access to its financial accounting documents and to audit such records and accounts both during and after the implementation of the Contract. In particular, the Contracting Authority may carry out whatever documentary or on-the-spot checks it deems necessary to find evidence in case of suspected unusual commercial expenses.
35. LIABILITY
Under no circumstances or for no reason whatsoever will the Back donor entertain any request for indemnity or payment directly submitted by the (Contracting Authority’s) contractors.
By this Code of Conduct, the Contracting Authority applies ethics to procurement. We expect our contractors to act socially and environmentally responsible and actively work for the implementation of the standards and principles in this Code of Conduct. The Code of Conduct is applicable for all our contractors who supply goods, services and works to our operations and projects.
This Code of Conduct and its related principles and standards are based on recommendations from the Danish Initiative for Ethical Trade (DIEH)[1], the UN Global Compact principles[2] and ECHO’s Humanitarian Aid Guidelines for Procurement 2011[3].
General Conditions
The Code of Conduct defines the ethical requirements and standards for our contractors, whom we expect to sign and respect the Code of Conduct, and work actively towards the implementation hereof. By signing the Code of Conduct contractors agree to place ethics central to their business activities.
The provision of the ethical standards constitutes minimum rather than maximum standards. International and national laws shall be complied with, and where the provisions of law and the Contracting Authority’s standards address the same subject, the highest standard shall apply.
It is the responsibility of the contractor to assure that their contractors and subcontractors comply with the ethical requirements and standards set forth in this Code of Conduct.
The Contracting Authority acknowledge that implementing ethical standards and ensuring ethical behaviour in our supply chain is a continuous process and a long term commitment for which we also have a responsibility. In order to achieve high ethical standards for procurement we are willing to engage in dialogue and collaboration with our contractors. In addition we expect our contractors to be open and willing to engage in dialogue with us to implement ethical standards for their businesses.
Unwillingness to co-operate or serious violations of the Code of Conduct will lead to termination of contracts.
Human Rights and Labour Rights
Contractors must at all times protect and promote human- and labour rights and work actively to address issues of concern. As a minimum they are obliged to comply with the following ethical standards:
- Respect for Human Rights (UN Universal Declaration of Human Rights)
The basic principles of the Universal Human Rights are that all human beings are born free and equal in dignity and in rights, and everyone has the right to life, liberty and security of the person. Contractors must not flaunt their responsibility to uphold and promote the Human Rights toward employees and the community in which they operate.
- Non exploitation of Child Labour (UN Child Convention on the Rights of the Child, and ILO Convention C138 & C182)
Contractors must not engage in the exploitation of child labour***[4]*** and contractors must take the necessary steps to prevent the employment of child labour. A child is defined as a person under the age of 18 and children shall not be engaged in labour that compromise their health, safety, mental and social development, and schooling. Children under the age of 15 (in developing countries 14) may not be engaged in regular work, but children above the age of 13 (in developing countries 12) can be engaged in light work if it does not interfere with compulsory schooling and is not harmful to their health and development.
- Employment is freely chosen (ILO Convention C29 & C105)
Contractors must not make use of forced or bonded labour and must respect workers freedom to leave their employer.
- Freedom of association and the right to collective bargaining (ILO Convention C87 & C98)
Contractors must recognise workers right to join or form trade unions and bargain collectively, and should adopt an open attitude towards the activities of trade unions (even if this is restricted under national law).
- Living wages are paid (ILO convention C131)
As a minimum, national minimum wage standards or ILO wage standards must be met by contractors. Additionally a living wage must be provided. A living wage is contextual, but must always meet basic needs such as food, shelter, clothing, health care and schooling and provide a discretionary income[5] - which is not always the case with a formal minimum wage.
- No discrimination in employment (ILO Convention C100 & C111 and the UN Convention on Discrimination against Women)
Contractors must not practice discrimination in hiring, salaries, job termination, retiring, and access to training or promotion - based on race, national origin, caste, gender, sexual orientation, political affiliation, disability, marital status, or HIV/AIDS status.
- No harsh or inhumane treatment of employees (ILO Convention C105)
The use of physical abuse, disciplinary punishment, sexual abuse, the threat of sexual and physical abuse, and other forms of intimidation may never be practiced by contractors.
- Working conditions are safe and hygienic (ILO Convention C155)
Contractors must take adequate steps to provide safe and hygienic working environments. Additionally workers safety must be a priority and adequate steps must be taken to prevent accidents and injury to health associated with or occurring in the course of work.
- Working hours are not excessive (ILO Convention C1 & C14)
Contractors must ensure that working hours comply with national law and international standards. A working week of 7 days should not exceed 48 hours and employees must have one day off per week. Overtime shall be compensated, limited and voluntary.
- Regular employment is provided (ILO Convention C143)
All Work performed must be on the basis of a recognised employment relationship established through international conventions and national law. Contractors must protect vulnerable group’s regular employment under these laws and conventions and must provide workers with a written contract.
International Humanitarian Law
Contractors linked to armed conflicts or operating in armed conflict settings shall respect civilian’s rights under International Humanitarian Law and not be engaged in activities which directly or indirectly initiate, sustain, and/or exacerbate armed conflicts and violations of International Humanitarian Law[6]. Contractors are expected to take a ‘do no harm’ approach to people affected by armed conflict.
Additionally, Contractors shall not be engaged in any other illegal activity.
Involvement in Weapon Activities
The Contracting Authority advocates for the Ottawa Convention against landmines and the Convention on Cluster Munitions against cluster bombs. Contractors shall not engage in any development, distribution, sale, or manufacturing of anti-personnel mines, cluster bombs, components, or any other weapon which feed into violations of International Humanitarian Law and Human Rights.
Protection of the Environment
The Contracting Authority wishes to minimise the environmental damages applied to nature via our procurement activities and we expect our suppliers and contractors to act in an environmentally responsible manner. This involves respecting applicable national and international environmental legislation and acting in accordance with the Rio Declaration.
As a minimum contractors should address issues related to proper waste management, ensuring recycling, conservation of scarce resources, and efficient energy use.
Anti-Corruption
Corruption is by the Contracting Authority defined as the misuse of entrusted power for private gain and it includes bribery, fraud, embezzlement and extortion. The Contracting Authority holds a great responsibility to avoid corruption and ensure high standards of integrity, accountability, fairness and professional conduct in our business relations. Contractors are expected to have the same approach by undertaking good and fair business ethics and practices, take action to prevent and fight corruption, and abide by international conventions as well as international and national laws. To fight corruption and promote transparency, contractors who are confronted with corrupt practices are advised to file a complaint in a Complaint Mechanism[7].
A contractor’s involvement in any form of corrupt practice during any stage of a selection process, in relation to the performance of a contract or in any other business context is unacceptable and will lead to the rejection of bids or termination of contracts.
List of International Conventions and Treaties covered by this Code of Conduct for Contractors
UN Universal Declaration of Human Rights, 1948; http://www.un.org/en/documents/udhr/index.shtml
Un Guiding Principles on Business and Human Rights, 2011;
http://www.ohchr.org/Documents/Publications/GuidingPrinciplesBusinessHR_EN.pdf
- Geneva Conventions I-IV, 1949 and additional Protocols;
http://www.icrc.org/eng/war-and-law/treaties-customary-law/geneva-conventions/index.jsp
ILO Declaration on Fundamental Principles and Rights at Work, 1998; http://www.ilo.org/declaration/lang--en/index.htm and http://www.ilo.org/wcmsp5/groups/public/---ed_norm/---declaration/documents/publication/wcms_095898....
UN Child Convention on the Rights of the Child, 1990; http://www2.ohchr.org/english/law/crc.htm
C182, Worst Forms of Child Labour Convention, 1999; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C182
C138, Minimum Age Convention, 1973; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C138
C87, Freedom of Association and Protection of the Right to Organise Convention, 1948; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C087
C98, Right to Organise and Collective Bargaining Convention, 1949; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C098
C29, Forced Labour Convention, 1930; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C029
C105, Abolition of Forced Labour Convention, 1957; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C105
C131, Minimum Wage Fixing Convention, 1970; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C131
C100, Equal Remuneration Convention, 1951; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C100
C111, Discrimination (Employment and Occupation) Convention, 1958; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C111
The UN Convention on the Elimination on All Forms of Discrimination against Women 1979; http://www.un.org/womenwatch/daw/cedaw/text/econvention.htm
C1, Hours of Work (Industry) Convention, 1919; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C001
C14, Weekly Rest (Industry) Convention, 1921; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C014
C143, Migrant Workers (Supplementary Provisions) convention, 1975; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C143
C155, Occupational Safety and Health Convention, 1981; http://www.ilo.org/ilolex/cgi-lex/convde.pl?C155
The Rio Declaration on Environment and Development, 1992; http://www.unep.org/Documents.Multilingual/Default.asp?DocumentID=78&ArticleID=1163&l=en
The Ottawa Convention, 1997; http://www.apminebanconvention.org/fileadmin/pdf/mbc/text_status/Ottawa_Convention_English.pdf
The Convention on Cluster Munitions, 2007; http://www.clusterconvention.org/files/2011/01/Convention-ENG1.pdf
Arms Trade Treaty, 2013; http://www.un.org/disarmament/ATT/
[2] http://www.unglobalcompact.org/AboutTheGC/TheTenPrinciples/
index.html
[3] http://ec.europa.eu/echo/partners/humanitarian_aid/procurement_guidelines_en.htm
[4] The definition of Child Labour can be found at: http://www.unglobalcompact.org/AboutTheGC/TheTenPrinciples/principle5.html and http://www.ilo.org/ilolex/cgi-lex/convde.pl?C138
[5] Discretionary income is the amount of an individual's income that is left for spending, investing, or saving after taxes and personal necessities (such as food, shelter, and clothing) have been paid.
[6] This includes pillage/looting which is the unlawful taking of private property for personal or private gain based on force, threats, intimidation, pressure and through a position of power accomplished due to the surrounding conflict.
[7] Contractors who have signed a contract with DCA, or DCA implementing partner, shall file a complaint through: http://www.danchurchaid.org/about-us/quality-assurance/anti-corruption/complaints
How to apply:
Date of issue: 04.11.2019
RFP no.: 177-38/M&E
Contract title:Research Consultant – “Socio-Economic Impact of Humanitarian Mine Action in Sirte”
Closing date: 15/11/2019 at 5pm Libya Local Time
Contracting Authority: DCA Libya Contact person: Wisam Kutom; Email: wiku@dca.dk